Greenland Opens Prequalification for 1,100 MW Hydropower Tender

Applicants must demonstrate at least DKK 10 billion in net worth. Applications are due May 1, 2027, and each final bid must include a project that can use the electricity.

The Government of Greenland has opened prequalification for Tasersiaq and Tarsartuup Tasersua, its largest and most studied hydropower resources. The Request for Qualifications facts, published Tuesday, November 24, 2026, set out who may apply and how to obtain the full documents. Applications are due by 12:00 noon Greenland time on May 1, 2027. The government expects to select the companies eligible for the final tender during 2027, according to a November 13 announcement. The full RfQ is not public; access costs DKK 225,000 (about $33,000).

Ane Wraae Nielsen, head of the Government of Greenland’s energy department, told GreenlandEnergy.com by email shortly before prequalification opened that Jens-Erik Kirkegaard had taken over responsibility for the tender from Jørgen “Juulut” Rosbach. Nielsen said the change in ministers had left the tender unchanged. “The tender is still very important for the Government of Greenland,” she said.

The sites lie between Kangerlussuaq and Nuuk. Together they have an estimated capacity of about 1,100 megawatts and expected annual production of about 9,600 gigawatt-hours. Tasersiaq (area 07.e) is the larger site, at about 820 MW. Tarsartuup Tasersua (06.g) is estimated at about 280 MW. The plan is to dam existing lakes at elevations of 650 to 700 meters, using catchments connected to the ice sheet, with most of the water expected to come from glacial melt.

In the final tender, companies may bid for one site, the other, or both. Each bid must include at least one offtake project able to use the power. Greenland has no interconnected national grid. A June 2025 government update said the two sites’ potential exceeds Greenland’s total energy demand several times over. The government expects the plants primarily to supply new industry.

An applicant must show a net worth of at least DKK 10 billion (about $1.46 billion) and average annual turnover of at least DKK 3 billion (about $439 million) over the past three financial years, using Danmarks Nationalbank’s November 23, 2026, rate of 683.30 kroner per $100. Further equity-ratio or credit-rating tests are set out only in the paid RfQ. Applicants must also show experience developing, planning, building, and operating at least one hydropower plant of 50 MW or more, and at least one relevant offtake project. Integrity, tax compliance, and the absence of sanctions or of circumstances that may pose a risk to national security or public order are required, as are satisfactory health, safety, and environmental systems. The public summary says the requirements apply to relevant consortium members and to outside entities whose capabilities the applicant relies on. It leaves open how their finances can be combined to meet the DKK 10 billion test.

Paid Advertisement

The fee is paid to the Greenland Self-Government. Applicants then email proof of payment to pan@nanoq.gl and receive access to the confidential documents through EU-Supply. The fee is refunded if an applicant meets the minimum requirements but is not selected. Submitting a prequalification application also counts as an application for a preliminary investigation license, with additional fees under Executive Order No. 21 of 17 June 2022.

“An investment screening process will be carried out for all applicants (and again in connection with the submission of final bids),” the facts page says. Inatsisartut has not yet adopted a standing screening law. Bill EM2026/214 had its first reading on November 10; the remaining readings are scheduled for spring 2027. (parliamentary status; bill text) As introduced, the bill would require prior permission for foreign investment in commercial hydropower plants and would enter into force on July 1, 2027.

Prequalification tests capacity. The later competition will score bids. In December 2025, Naalakkersuisut adopted a government-take model that applies only to the hydropower plants, not to the offtake industry. It has two competitive elements: a resource rent per unit of energy produced, and government co-ownership through preference shares issued without a capital contribution. (Government take model, January 7, 2026) The relative weighting of the final tender parameters was not published. Bids are to be evaluated on financial returns to the Self-Government; on offtake industry near inhabited communities and jobs that allow daily commuting; and on project feasibility. Those criteria grew in part from public meetings in spring 2026 and talks with Qeqqata Municipality.

On November 3, Inatsisartut adopted amendments (EM2026/228) allowing initial hydropower exploitation licenses of up to 60 years, up from 40, effective January 1, 2027. The maximum, including extensions, remains 80 years. (Greenland Approves Longer Hydropower Licenses to Support Investment)

Greenland had already announced plans to screen foreign investment in the projects on September 1. After signing the defense agreement with Denmark and the United States on September 22, the government delayed prequalification to revise the tender documents. Tuesday’s facts page confirms that applicants will be screened and that final bidders will be screened again. It leaves two questions open: what the agreement changed for bidders, and how Greenland will conduct the first round of screening.

GreenlandEnergy.com provides independent analysis of Greenland’s energy landscape, critical minerals development, and Arctic geopolitics. For corrections or feedback: press@greenlandenergy.com